Analisa Beton K 300

Analisa Harga Satuan Pekerjaan Beton K 300 / m3  Material Semen 8,260 sak @ 65.000 = 536.900 Pasir Beton 0,486 m3 @ 210.000 = 102.060 Kerikil 0,756 m3 @ 205.000 = 154.980 Air 215,000 liter @ 5 = 1.075 Subtotal = 795.015 Upah Pekerja 1,650 OH @ 70.000 = 115.500 Read more…

Analisa Beton K 350

Analisa Harga Satuan Pekerjaan Beton K 350 / m3  Material Semen 8.960 sak @ 65.000 = 582.400 Pasir Beton 0,476 m3 @ 210.000 = 99.960 Kerikil 0,741 m3 @ 205.000 = 151.905 Air 215,000 liter @ 5 = 1.075 Subtotal = 835.340 Upah Pekerja 1,650 OH @ 70.000 = 115.500 Read more…

Analisa Beton K 125

Analisa Harga Satuan Pekerjaan Beton K 125 / m3 Material Semen 5,520 sak @ 65.000 = 358.800 Pasir Beton 0,591 m3 @ 210.000 = 124.110 Kerikil 0,750 m3 @ 205.000 = 153.750 Air 215,000 liter @ 5 = 1.075 Subtotal = 637.735 Upah Pekerja 1,650 OH @ 70.000 = 115.500 Read more…

Campuran Beton K 300 Manual

Cara Mengetahui Komposisi Campuran Beton K 300 Manual Yang Tepat Dalam sebuah pembangunan, sudah umum rasanya kontraktor maupun ahli bangunan akan mencampurkan adukan beton sehingga menciptakan beton yang memiliki mutu tinggi dan baik, mutu sedang, bahkan beton bermutu rendah. Salah satunya campuran beton k 300 manual. Beton campuran K 300 Read more…

Tukang Cor Beton

PEKERJAAN PERSIAPAN PENGECORAN BETON Peninjauan lokasi pekerjaan pengecoran beton Di dalam pekerjaan persiapan salah satunya pengaturan sebelum pekerjaan dimulai, pekerjaan tersebut mencakup peninjauan lapangan, persiapan pekerjaan dan mobilisasi dimaksudkan agar pekerjaan yang dilaksanakan dapat terselesaikan dengan sedikit resiko terhadap gangguan keterlambatan penyelesaian Peninjauan area yang akan dicor Apabila seorang mandor Read more…